7 A team of workers took 74.7 hours to complete the project. A smaller team of workers willcomplete the same task, but it will take them 1.15 times as long as it took the first team.Based on this information, which statement is true?A The task will take the smaller team of workers 64.3 hours to complete, because74.7 - 1.15 = 64.3.B The task will take the smaller team of workers 75.85 hours to complete, because74.7 + 1.15 = 75.85.C The task will take the smaller team of workers 85.905 hours to complete, because 74.7 x1.15 = 85.905.D The task will take the smaller team of workers 86.250 hours to complete, because 74.7x 1.15 = 86.250.

7 A team of workers took 74.7 hours to complete the project. A smaller team of workers-example-1

1 Answer

3 votes

Problem: a team of workers took 74.7 hours to complete the project. A smaller team of workers will complete the same task, but it will take them 1.15 times as long as it took the first team.

Solution: The small group takes the following amount of time to do the same task as the other group (first group):


t\text{ = 1.15 x 74.7 hours = 85.905}

So for A, B, and D, they are all false. but C is true.

User Jstngoulet
by
8.5k points