A contractor hired 150 workers to pave 30 miles of highway how many workers will they need to hire to pave 20 miles of highway in the same amount of time?

1 Answer

6 votes

Answer: 100

Explanation:

First, we need to know how many workers must be hired to pave one mile.
Which is 5 workers per 1 mile ( 150 / 30 )

Then you can either do
(5 + 5 +5 +5 + 5) + (5 + 5 +5 +5 + 5) + (5 + 5 +5 +5 + 5) + (5 + 5 +5 +5 + 5)
OR
5 x 20 = 100

( if I'm wrong it's like 3 am so I'm a bit slow but I hope I helped )