10 workers can finish the job in 15 days. For the first 5 days, only 6 workers worked on the job. Then for the next 3 days 2 more workers joined them. To finish the job, 4 more workers joined

them. After how many days was the whole job done?
A. 8days
B. 12days
C. 16days
D. 18days​

User Ealione
by
8.5k points

1 Answer

2 votes

Answer:

C. 16 days

Explanation:

Let´s say each worker does 1 ¨work¨, for each day, in order to complete the job in 15 days. That´s a total of 150 work.

If only 6 workers worked for the first 5 days, then we only do 30 by Day 5.

2 more workers join, so they do 8 work each day, 24 work in 3 days, 54 work by Day 8.

4 more workers join to complete the job, so we now do 12 work each day.

150 - 54 = 96

96 work is left to do, which would be done in 8 days by 12 workers.

8 days + 8 days = 16 days

User John Zhao
by
8.5k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories