10 workers can finish the job in 15 days. For the first 5 days, only 6 workers worked on the job. Then for the next 3 days 2 more workers joined them. To finish the job, 4 more workers joined

them. After how many days was the whole job done?
A. 8days
B. 12days
C. 16days
D. 18days​

User Ealione
by
3.6k points

1 Answer

2 votes

Answer:

C. 16 days

Explanation:

Let´s say each worker does 1 ¨work¨, for each day, in order to complete the job in 15 days. That´s a total of 150 work.

If only 6 workers worked for the first 5 days, then we only do 30 by Day 5.

2 more workers join, so they do 8 work each day, 24 work in 3 days, 54 work by Day 8.

4 more workers join to complete the job, so we now do 12 work each day.

150 - 54 = 96

96 work is left to do, which would be done in 8 days by 12 workers.

8 days + 8 days = 16 days