519,151 views
35 votes
35 votes
if 16 men can finish to contruct a bulding in 40 days how manny more men are needed to finish the contruction in 32 days​

User Mukul Kumar
by
2.6k points

1 Answer

18 votes
18 votes

Answer:

20 mens are needed to contruct a building in 32 days.

User Feilong
by
3.1k points