if 16 men can finish to contruct a bulding in 40 days how manny more men are needed to finish the contruction in 32 days
Mukul Kumar
asked
Sep 28, 2022
519,150
views
35
votes
35
votes
if 16 men can finish to contruct a bulding in 40 days how manny more men are needed to finish the contruction in 32 days
Mathematics
high-school
Mukul Kumar
asked
Sep 28, 2022
by
Mukul Kumar
2.6k
points
answer
comment
share this
share
0 Comments
Your comment on this question:
Email me at this address if a comment is added after mine:
Email me if a comment is added after mine
Privacy: Your email address will only be used for sending these notifications.
Add comment
Cancel
Your answer
Email me at this address if my answer is selected or commented on:
Email me if my answer is selected or commented on
Privacy: Your email address will only be used for sending these notifications.
Add answer
Cancel
1
Answer
18
votes
18
votes
Answer:
20 mens are needed to contruct a building in 32 days.
Feilong
answered
Oct 4, 2022
by
Feilong
3.1k
points
ask related question
comment
share this
0 Comments
Your comment on this answer:
Email me at this address if a comment is added after mine:
Email me if a comment is added after mine
Privacy: Your email address will only be used for sending these notifications.
Add comment
Cancel
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
1.6m
questions
2.0m
answers
Other Questions
Can anybody tell me what’s going on here?
Evalute 8a -1+0.5b when a =1/4 and b= 10 how dose this work i need help..
PLZ needed now plz URGENT!
HELP PLEASE, I NEED THE ANSWER QUICKLY
Yall help me out please
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org