Answer:
Budgeted manufacturing overhead rate in the machining department is $49.00 per machine hour. In the finishing department is $52.78 per direct labor hour.
Step-by-step explanation:
Budgeted manufacturing overhead rate = Budgeted Overheads ÷ Budgeted Activity
Note that ;
1. Machining department has machine- hours as the allocation base.
2.Finishing department has direct manufacturing labor costs as the allocation base
Therefore,
Budgeted manufacturing overhead rate (Machining department) = $9,065,000 ÷ 185,000 = $49.00 per machine hour
Budgeted manufacturing overhead rate (Finishing department) = $8,181,000 ÷ 155,000 = $52.78 per direct labor hour
Conclusion
Budgeted manufacturing overhead rate in the machining department is $49.00 per machine hour. In the finishing department is $52.78 per direct labor hour.