Answer:
$188,900
Step-by-step explanation:
The computation of the total cost of JOb A is shown below:
= Work in process + material requistioned + direct labor + applied overhead
= $33,400 + $76,000 + 5,300 × $8.50 + 5,300 × $617,500 ÷ 95,000
= $33,400 + $76,000 + $45,050 + $34,450
= $188,900