The WBS is best suited for design and construction projects that have tangible outcomes. When the final outcome of the project is less tangible or it is the result of a series of steps or phases, some project managers choose to utilize a(n) ___________. Multiple Choice Responsibility Matrix (RM) Organization Breakdown Structure (OBS) Work Breakdown Structure (WBS) Modified Process Breakdown Structure (PBS) Project Priority Matrix (PPM)

User Ebenezar John Paul
by
3.0k points

1 Answer

20 votes
20 votes

Answer:

Process Breakdown Structure (PBS)

Step-by-step explanation:

Since in the question it is mentioned that WBS should be best suited for design & construction projects so there is tangible results

now if the final result should be lower tangible so here the project manager should select the project breakdown structure as the process of the project should be driven via requirement of the performance but not with the plans or the blueprints