Answer:
16 days
Explanation:
Here,
By the question,
4 men takes 4 days working each day 4 hours to complete 4 units of work..
then..
if 1 man works 1 hour each day then i would take ( 4×4×4 ) days
= 64days
then..
if 2 men work for 2 hours per day then.
it would take
4×4×4 / 2×2 days
= 16 days