If 4 men working 4 hours for 4 days complete 4 units of work, then how many units of work will be completed by 2 men working for 2 hours per day in 2 days.​

User Yoori
by
2.8k points

2 Answers

14 votes
14 votes

Answer:

16 days

Explanation:

Here,

By the question,

4 men takes 4 days working each day 4 hours to complete 4 units of work..

then..

if 1 man works 1 hour each day then i would take ( 4×4×4 ) days

= 64days

then..

if 2 men work for 2 hours per day then.

it would take

4×4×4 / 2×2 days