Answer:
Direct material quantity variance= $12,000 unfavorable
Step-by-step explanation:
To calculate the direct material quantity variance, we need to use the following formula:
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (1.5*12,000 - 19,500)*8
Direct material quantity variance= (18,000 - 19,500)*8
Direct material quantity variance= $12,000 unfavorable