163k views
3 votes
site work for a new professional centre includes the construction of a parking lot. the parking lot is 79 ft at its longest dimension and 62 ft at its shortest measured along the outside. a concrete retaining wall is required on three sides of the parking lot, the two longer sides and one short side. determine the quantity of rebar needed for the continuous footings. allow for 3 inches of cover. add 10 percent for lap and waste to the continuous bars.

User Mesutozer
by
7.4k points

1 Answer

2 votes

Answer:

–✦– < < –✦–

Explanation:

To determine the quantity of rebar needed for the continuous footings of the concrete retaining wall, we'll follow these steps:

1. **Calculate the length of rebar needed for each side:**

- The total length of rebar needed for each side is equal to the perimeter of the corresponding side plus an additional length for laps and waste.

2. **Calculate the perimeter of each side:**

- Use the dimensions of the parking lot to find the perimeter of each side. The formula for the perimeter of a rectangle is \( P = 2 \times (L + W) \), where \( L \) is the length and \( W \) is the width.

3. **Determine the total length of rebar for each side:**

- Add the calculated perimeter to the additional length for laps and waste.

4. **Calculate the total quantity of rebar needed:**

- Sum up the lengths calculated for each side.

Now, let's go through the calculations:

Given dimensions:

- Length of the parking lot (\(L\)): 79 ft

- Width of the parking lot (\(W\)): 62 ft

- Cover: 3 inches (convert to feet: \(3/12\))

- Additional for lap and waste: 10% of the calculated rebar length

**Calculations:**

1. **Length of rebar for the longer sides:**

- Perimeter: \( P_{\text{long}} = 2 \times (79 + 62) \)

- Total length: \( L_{\text{long}} = P_{\text{long}} + 2 \times \text{Cover} + 0.10 \times P_{\text{long}} \)

2. **Length of rebar for the shorter side:**

- Perimeter: \( P_{\text{short}} = 2 \times (62 + 3) \)

- Total length: \( L_{\text{short}} = P_{\text{short}} + 2 \times \text{Cover} + 0.10 \times P_{\text{short}} \)

3. **Total quantity of rebar needed:**

- \( L_{\text{total}} = L_{\text{long1}} + L_{\text{long2}} + L_{\text{short}} \)

Now, plug in the values and perform the calculations. Note that all measurements are in feet.

\[ P_{\text{long}} = 2 \times (79 + 62) = 282 \, \text{ft} \]

\[ L_{\text{long}} = P_{\text{long}} + 2 \times (3/12) + 0.10 \times P_{\text{long}} \]

Calculate \( L_{\text{short}} \) in a similar manner.

Finally, calculate \( L_{\text{total}} = L_{\text{long1}} + L_{\text{long2}} + L_{\text{short}} \) to find the total quantity of rebar needed.

User Slhddn
by
8.5k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.