12 workers take 4 hours to complete a job. How long would it take 15 workers to complete the job?​

User Toholio
by
8.2k points

1 Answer

3 votes

Answer:

3 hours and 12 minutes

Explanation:

In order to solve this problem, we can use the formula:


\sf workers * time = work

We know that 12 workers take 4 hours to complete a job.

Therefore, we can say:


\sf 12 * 4 = work

Solving for work we get:

work = 48 hours

Now, we need to find out how long it would take 15 workers to complete the same job.

Let's call this time x. We can set up another equation:


\sf 15 * x = 48

Solving for x, we get:


\sf x= (48 )/(15 )= 3.2

In hours and minutes, it can be expressed as:


\textsf{3 hours and 20\% of 60 minutes }


\textsf{3 hours and }\sf (20)/(100)* 60\textsf{ minutes }


\textsf{3 hours and 12 minutes }

Therefore, it would take 3 hours and 12 minutes for 15 workers to complete the job.

User Mspoulsen
by
8.1k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories