Weisman, Inc. uses activity-based costing as the basis for information to set prices for its six lines of seasonal coats.

Activity Cost Pools Estimated Overhead Estimated Use of Cost Drivers per Activity
Designing $448,260 12,400 designer hours
Sizing and cutting 4,009,050 151,000 machine hours
Stitching and trimming 1,419,075 79,500 labor hours
Wrapping and packing 299,250 31,500 finished units

Compute the activity-based overhead rates using the following budgeted data for each of the activity cost pools.

a. Designing
b. Sizing and cutting
c. Stitching and trimming
d. Wrapping and packing

User Omoba
by
2.8k points

1 Answer

5 votes
5 votes

Answer and Explanation:

The computation of the activity based overhead rate is shown below:

= Estimated overhead ÷ cost driver per activity

a. For designing

= $448,260 ÷ 12,400

= $36.15 per design hour

b. For sizing and cutting

= $4,009,050 ÷ 151,000

= $26.55 per machine hour

c. For stiching and trimming

= $1,419,075 ÷ 79,500

= $17.85 per labor hour

d. For wrapping and packing

= $299,250 ÷ 31,500

= $9.5 per finished units