The preparation of a formal SEMP is usually a required portion of a contractor’s proposal for a competitive system development program. Since at this time the system design is still in a conceptual state, explain where you would get the information to address the elements of a typical SEMP as listed in this chapter.

User Cameo
by
3.3k points

1 Answer

5 votes

Answer:

hello you question lacks the listed options hence i will give you a general answer

answer :

Information can be gotten from : living document and product engineering and RMA engineering

Step-by-step explanation:

SEMP ( system engineering management plan ) is a plan laid out to enable communication between the project management team in a project and the engineering team working on the project .

The information to be used to address the elements of a typical SEMP at the conceptual stage can gotten from the living document and it will continue to be improved on as the project frame work continues to expand gradually also Information to address the elements of a typical SEMP can be gotten from product engineering and RMA engineering because an SEMP is based on several engineering process