57.6k views
5 votes
A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they work for 8 hours per day. After 20 working days, he finds that only 1200 m of the road is completed. How many more men does he need to employ in order to finish the project on time if each man now works 10 hours a day?​

User Azarro
by
7.8k points

1 Answer

2 votes

Answer:

Since the contractor already has 50 men, he needs to employ an additional 71 men to complete the project on time.

Explanation:

Let's first find the total amount of work needed to be done, using the given information that the road is 3000 m long:

Total amount of work = 3000 m

We know that 50 men are employed and they work 8 hours per day. So the total man-hours worked in 20 days can be calculated as:

Total man-hours worked in 20 days = 50 men x 8 hours/day x 20 days = 8000 man-hours

We also know that only 1200 m of the road is completed in 20 days. So the amount of work remaining can be calculated as:

Remaining amount of work = Total amount of work - Completed work

Remaining amount of work = 3000 m - 1200 m = 1800 m

Now, we can calculate the total number of man-hours required to complete the remaining work:

Total man-hours required = Remaining amount of work / Productivity rate

Productivity rate = (8000 man-hours) / (1200 m) = 6.67 man-hours/m

Total man-hours required = (1800 m) x (6.67 man-hours/m) = 12,006 man-hours

To complete the remaining work in 10 days, each man needs to work 10 hours per day. Therefore, the total number of men required can be calculated as:

Total men required = Total man-hours required / (Hours per day x Days available)

Total men required = 12,006 man-hours / (10 hours/day x 10 days)

Total men required = 120.06

Rounding up to the nearest whole number, the contractor needs to employ 121 men.

User Jrook
by
8.5k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories