57.6k views
5 votes
A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they work for 8 hours per day. After 20 working days, he finds that only 1200 m of the road is completed. How many more men does he need to employ in order to finish the project on time if each man now works 10 hours a day?​

User Azarro
by
7.8k points

1 Answer

2 votes

Answer:

Since the contractor already has 50 men, he needs to employ an additional 71 men to complete the project on time.

Explanation:

Let's first find the total amount of work needed to be done, using the given information that the road is 3000 m long:

Total amount of work = 3000 m

We know that 50 men are employed and they work 8 hours per day. So the total man-hours worked in 20 days can be calculated as:

Total man-hours worked in 20 days = 50 men x 8 hours/day x 20 days = 8000 man-hours

We also know that only 1200 m of the road is completed in 20 days. So the amount of work remaining can be calculated as:

Remaining amount of work = Total amount of work - Completed work

Remaining amount of work = 3000 m - 1200 m = 1800 m

Now, we can calculate the total number of man-hours required to complete the remaining work:

Total man-hours required = Remaining amount of work / Productivity rate

Productivity rate = (8000 man-hours) / (1200 m) = 6.67 man-hours/m

Total man-hours required = (1800 m) x (6.67 man-hours/m) = 12,006 man-hours

To complete the remaining work in 10 days, each man needs to work 10 hours per day. Therefore, the total number of men required can be calculated as:

Total men required = Total man-hours required / (Hours per day x Days available)

Total men required = 12,006 man-hours / (10 hours/day x 10 days)

Total men required = 120.06

Rounding up to the nearest whole number, the contractor needs to employ 121 men.

User Jrook
by
8.5k points

No related questions found