'which of the following is not a best practice for new product development projects? group of answer choices assign project managers to lead projects. select projects that will take less than two years to provide payback. focus on customer needs in identifying projects. align projects and resources with

1 Answer

3 votes

New Product Development Project

Project should not be selected based on the payback period, but it should be carefully examined before taking it. Hence, the correct option is b.