A construction crew has just built a new road. They built the road at a rate of 3 kilometers per week. They built 93.75 kilometers of road. How many weeks did it take them?

User Zemzela
by
7.9k points

1 Answer

3 votes

Answer:

31.25 weeks

Explanation:

You want to know how many weeks it took to construct 93.75 km of road at the rate of 3 km/week.

Time

The relation between time, rate, and quantity is ...

time = quantity/rate

time = (93.75 km)/(3 km/wk) = (93.75/3) wk = 31.25 wk

It took the crew 31.25 weeks to build 93.75 km of road.