The longest path through the network, in terms of time, is referred to as the

a) activity-on-node path
b) path of greatest slack
c) critical path
d) scheduling path

User Humayun
by
9.0k points

1 Answer

3 votes

Final answer:

The longest path through the network, in terms of time, is known as the critical path, which dictates the minimum project duration.

Step-by-step explanation:

The longest path through the network, in terms of time, is referred to as the critical path. The critical path is a project management term that describes the sequence of stages determining the minimum time needed for an operation. It is the longest duration path through a network diagram and determines the shortest time possible to complete the project. Any delays on the critical path will delay the completion of the entire project.

Options a) activity-on-node path and d) scheduling path refer to methods of representing the activities in a network, but not necessarily the longest duration. The b) path of greatest slack refers to a path with the most buffer time and, therefore, is not the critical path that requires the most time.