218k views
1 vote
What is the primary purpose of conducting stakeholder mapping in the project planning phase?

A) To assign tasks to stakeholders.
B) To identify and group project stakeholders.
C) To estimate project budget and timelines.
D) To create the project's mission statement.

User Sachy
by
8.4k points

1 Answer

4 votes

Final answer:

The primary purpose of conducting stakeholder mapping in the project planning phase is to identify and group project stakeholders.

Step-by-step explanation:

The primary purpose of conducting stakeholder mapping in the project planning phase is B) To identify and group project stakeholders.

Stakeholder mapping involves identifying and categorizing all individuals, groups, or organizations that have an interest in or can be affected by the project. It helps project managers understand the different stakeholders, their roles, and their level of influence. By mapping stakeholders, project teams can effectively engage and communicate with them throughout the project, ensuring their needs and expectations are taken into account, and minimizing potential risks and conflicts.

User Peter Bromberg
by
8.7k points