Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2018.At December 31, 2018, Seasons estimates that it is 30% complete with the construction, based on costs incurred. What is the total amount of Revenue and Profit from Long-Term Contracts recognized for 2018?

User Touchpad
by
4.7k points

1 Answer

3 votes

Answer:

The correct answer is "$5,580,000".

Step-by-step explanation:

The given values are:

Total contract price,

= $18,600,000

Completion percentage,

= 30%

Seasons estimates,

= $17,750,000

Now,

In 2018,

The total amount of revenue will be:

=
Total \ contract \ price* Completion \ percentage

On substituting the given values, we get

=
18,600,000* 30 \ percent

=
5,580,000 ($)