What is the expected completion time of this project?

a. 1.14 hrs
b. 8.5 hrs
c. none of the above
d. 8 hrs

1 Answer

0 votes

Final answer:

The expected completion time of the project is 8 hrs.

Step-by-step explanation:

The expected completion time of the project can be determined by considering the given options. Option a states that the expected completion time is 1.14 hrs, which is less than seven hours. Option b states that the expected completion time is 8.5 hrs, which is more than seven hours.

Option c states that none of the above options is the expected completion time. Option d states that the expected completion time is 8 hrs, which is less than seven hours.

Therefore, the correct answer is d. 8 hrs, as it satisfies the condition of being less than seven hours.