2 printing machines of a printing house can complete the printing work of the required number of Excel in Mathematics textbooks in 20 days. After printing the books for 8 days, if 1 more machine was added, in how many days would the remaining work be completed? ​

1 Answer

1 vote

After printing the books for 8 days, if 1 more machine was added, the number of days in which the remaining work would be completed is 8 days.

Based on the information provided above, the total number of days which the 2 printing machines can complete the printing in 20 days can be calculated as follows;

Total number of days (2 printing machines) = 2 × 20

Total number of days (2 printing machines) = 40 days.

For the total number of days in printing the books for 8 days, we have the following:

Total work days = 2 × 8

Total work days = 16 days.

Next, we would determine the number of days that are remaining as follows;

Remaining days = Total number of days (2 printing machines) - Total work days

Remaining days = 40 - 16

Remaining days = 24 days.

Since 1 more printing machine will be added, the total number of machine becomes 3 printing machines. Therefore, we would divide the remaining days by 3 as follows;

Number of days to complete the work = 24/3

Number of days to complete the work = 8 days.

User Alexander Santos
by
8.0k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories