Answer:
The work will be finished in 10 days.
Explanation:
Rashid can do a piece of work in 8 days
This means that each day he works, Rashid does
of the work.
Tipu can finish in 12 days.
This means that each day he works, Tipu does
of the work.
Each 2 days:
Each 2 days they work, the amount done is given by:

Each 2 days, 5/24 of the work is done:
The number of periods of 2 days that is needed to finish the work(100% = 1 completed), is given by:

2*4.8 = 9.6
Rounding up
The work will be finished in 10 days.