Which of the following represent best practices in developing a work breakdown structure? (choose all that apply)

⚪ Include a risk analysis
⚪. Each work package should include a noun and a verb.
⚪ Think Hierarchically
⚪ Use sticky notes
⚪ Target low level tasks with 8-80 hours duration.
⚪ For complex projects, have two separate teams develop their own WBS and then get together to compare results.

User Liam M
by
8.2k points

1 Answer

2 votes

Include a risk analysis

Each work package should include a noun and a verb

Think Hierarchically

Target low-level tasks with 8-80 hours duration

Options A, B, C and E

The following represent best practices in developing a work breakdown structure (WBS):

Include a risk analysis: Incorporating a risk analysis helps in identifying potential risks associated with different tasks or components within the WBS.

Each work package should include a noun and a verb: Work packages should be clearly defined using specific actions (verbs) and deliverables (nouns) to ensure clarity and understanding.

Think Hierarchically: Organize the WBS in a hierarchical manner, breaking down larger tasks into smaller, manageable components.

Target low-level tasks with 8-80 hours duration: Work packages should be of a manageable size, typically falling within the range of 8 to 80 hours for effective planning and execution.