During which phase is a rough top-down estimate likely, and during which phase is a detailed bottom-up estimate likely in the subject of Project Management?

A) Rough top-down estimate: Initiation phase; Detailed bottom-up estimate: Execution phase.
B) Rough top-down estimate: Execution phase; Detailed bottom-up estimate: Initiation phase.
C) Rough top-down estimate: Planning phase; Detailed bottom-up estimate: Execution phase.
D) Rough top-down estimate: Execution phase; Detailed bottom-up estimate: Planning phase.

User Amin Eshaq
by
7.9k points

1 Answer

5 votes

Final answer:

In project management, a rough top-down estimate is used during the initiation phase, while a detailed bottom-up estimate is likely during the planning phase.

Step-by-step explanation:

In project management, a rough top-down estimate is typically used during the initiation phase, while a detailed bottom-up estimate is more likely during the planning phase.

During the initiation phase, project managers may use high-level information or historical data to provide a quick estimate of the project's cost and duration. This estimate helps in determining the feasibility of the project and securing approval to move forward.

During the planning phase, a detailed bottom-up estimate is created by breaking down the project into smaller tasks and estimating the effort, time, and resources required for each task. This estimate provides a more accurate and detailed understanding of the project's scope, cost, and schedule.

User Falgantil
by
8.4k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories