During which phase is a rough top-down estimate likely, and during which phase is a detailed bottom-up estimate likely in the subject of Project Management?

A) Rough top-down estimate: Initiation phase; Detailed bottom-up estimate: Execution phase.
B) Rough top-down estimate: Execution phase; Detailed bottom-up estimate: Initiation phase.
C) Rough top-down estimate: Planning phase; Detailed bottom-up estimate: Execution phase.
D) Rough top-down estimate: Execution phase; Detailed bottom-up estimate: Planning phase.

User Amin Eshaq
by
7.9k points

1 Answer

5 votes

Final answer:

In project management, a rough top-down estimate is used during the initiation phase, while a detailed bottom-up estimate is likely during the planning phase.

Step-by-step explanation:

In project management, a rough top-down estimate is typically used during the initiation phase, while a detailed bottom-up estimate is more likely during the planning phase.

During the initiation phase, project managers may use high-level information or historical data to provide a quick estimate of the project's cost and duration. This estimate helps in determining the feasibility of the project and securing approval to move forward.

During the planning phase, a detailed bottom-up estimate is created by breaking down the project into smaller tasks and estimating the effort, time, and resources required for each task. This estimate provides a more accurate and detailed understanding of the project's scope, cost, and schedule.