A certain number of men can do a work in 60 days. If there were 8 men less, it could be finished in 10 days more. The number of men is:

(a) 20 men
(b) 25 men
(c) 30 men
(d) 35 men

1 Answer

7 votes

Final answer:

To find the number of men, we need to set up an equation using the concept of man-days and solve for x. The value of x represents the number of men needed to complete the work.

Step-by-step explanation:

To solve this problem, let's assume the number of men who can do the work in 60 days is x.

We are given that if there were 8 men less, it would take 10 days more to finish the work. This means that the number of men decreases to (x - 8) and the number of days increases to (60 + 10).

Next, we can use the concept of man-days, where the number of men multiplied by the number of days gives the total work done. So, we can set up the equation: x * 60 = (x - 8) * (60 + 10).

Solving this equation will give us the value of x, which represents the number of men.

After solving the equation, we find that x = 30. Therefore, the number of men is 30.

User Farhad Navayazdan
by
8.8k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories