You have successfully erected some cast-in-place concrete and remove the forms. You had the shoring equipment inspected before you began, but the latest inspection shows there is some damage to the equipment. What should you do?

1) Put it aside until you can get the right parts to repair it.
2) See if you can find some different equipment.
3) Immediately reinforce the equipment so that it is in good working order.
4) Use it for one more day, and then have it inspected again.

User Tunga
by
8.0k points

1 Answer

2 votes

Final answer:

If the shoring equipment used for the cast-in-place concrete shows damage during the latest inspection, it is important to put it aside until it can be repaired with the right parts.

Step-by-step explanation:

If the shoring equipment used for the cast-in-place concrete shows damage during the latest inspection, it is important to take appropriate action for the safety and integrity of the structure. The recommended course of action would be to put the damaged equipment aside until you can get the right parts to repair it. Continuing to use damaged shoring equipment can compromise the structural stability and increase the risk of accidents or failures.