Select the information that is true about lift-slab operations. Select all that apply and then click the DONE button.

1) The operations must be designed and planned by a registered professional engineer who has experience in lift-slab construction.
2) Lift-slab is a rarely used method for concrete construction.
3) The lift slab plans and designs must have detailed instructions and sketches on the method of erection.
4) Anyone is allowed to implement the plans.

1 Answer

1 vote

Final answer:

Lift-slab operations involve the lifting and placement of precast concrete slabs to form a structure. They must be designed by a registered professional engineer, include detailed instructions, and should only be implemented by trained professionals.

Step-by-step explanation:

Lift-slab operations refer to a construction method in which precast concrete slabs are lifted and placed in position to form the structure. It is important that the operations are designed and planned by a registered professional engineer with experience in lift-slab construction, ensuring proper safety and structural integrity. Therefore, statement 1 is true.

Contrary to statement 2, lift-slab is a commonly used method for concrete construction, especially for multi-story buildings. It offers speed and efficiency in construction.

Furthermore, detailed instructions and sketches on the method of erection are indeed necessary for lift-slab construction, as stated in statement 3. These plans and designs help ensure the proper execution of the lifting process.

However, statement 4 is false. Only trained professionals who have the expertise and knowledge should implement the lift-slab plans to ensure the safety and quality of the construction.