In SAFe®, which two items belong in the Team Backlog? (Choose two.)

a) Features
b) Epics
c) User stories
d) Program backlog items

User Edgerunner
by
8.1k points

1 Answer

1 vote

Final answer:

In SAFe®, the Team Backlog consists of user stories and program backlog items.

Step-by-step explanation:

In SAFe®, the two items that belong in the Team Backlog are User stories and Program backlog items. User stories are small, concise descriptions of desired system functionality, while Program backlog items are the larger, more complex items that are broken down into smaller user stories. Features and epics, on the other hand, belong in the Program Backlog, where they are further refined and prioritized.