Who is responsible for preparing Change orders and CCDs? Where is this responsibility given?

a) Architect - B101
b) Contractor - A201
c) Owner - B101
d) Civil engineer - A201

1 Answer

3 votes

Final answer:

The Architect is responsible for preparing Change Orders and CCDs as per the AIA B101 agreement delineates the contractor's responsibilities but does not directly assign the task of preparing Change Orders and CCDs to the contractor..

Step-by-step explanation:

The responsibility for preparing Change Orders and Construction Change Directives (CCDs) typically lies with the Architect of the project. This responsibility is outlined in the American Institute of Architects (AIA) document B101, which is a standard form of agreement between the owner and the architect. Specifically, the architect is tasked with preparing Change Orders and Construction Change Directives in consultation with the owner and the contractor as part of their contractual duties. The document A201, known as the General Conditions of the Contract for Construction, delineates the contractor's responsibilities but does not directly assign the task of preparing Change Orders and CCDs to the contractor.

In the context of construction projects, the responsibility for preparing change orders and Construction Change Directives (CCDs) is typically given to the Contractor. This is stated in the A201 general conditions document, which is a standard form contract published by the American Institute of Architects (AIA).