The standard for direct materials for product A is 6 square feet at $10 per square foot. If a firm produces 100 units of product A and uses 600 square feet at $11 per square foot the materials price variance is:

A) $660 unfavorable
B) $660 favorable
C) $600 unfavorable
D) $600 favorable

User KarateKid
by
8.2k points

1 Answer

2 votes

Final answer:

The materials price variance is calculated by subtracting the standard cost from the actual cost, resulting in a $600 unfavorable variance, indicating that the firm spent more on materials than the standard cost.

Step-by-step explanation:

The materials price variance for the situation where the standard for direct materials for product A is 6 square feet at $10 per square foot and if a firm produces 100 units of product A and uses 600 square feet at $11 per square foot can be calculated as follows:

Standard Cost = Standard quantity × Standard price = 600 square feet × $10 per square foot = $6,000.

Actual Cost = Actual quantity × Actual price = 600 square feet × $11 per square foot = $6,600.

Materials Price Variance = Actual Cost - Standard Cost = $6,600 - $6,000 = $600 unfavorable.

Therefore, the materials price variance is $600 unfavorable, meaning the firm spent $600 more on materials than the standard cost.

User Max Baldwin
by
8.0k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories