186k views
4 votes
You can use a task calendar to schedule a task that will occur during working time that is not available on the project calendar.

a) True
b) False

User Langtu
by
6.8k points

1 Answer

5 votes

Final answer:

The correct answer is 'False'; tasks cannot be scheduled during unavailable working times as per the project calendar. The project calendar reflects when resources can be utilized, taking into account holidays and non-working hours.

Step-by-step explanation:

To answer the student's question: you cannot use a task calendar to schedule a task during a time that is not available on the project calendar; therefore, the correct answer would be b) False. When managing a project, it's crucial to ensure that tasks are scheduled during times when resources are actually available. The project calendar defines the working days and hours for tasks in a project, including holidays and non-working periods. If a resource is not available according to the project calendar, trying to schedule a task in this time would typically not be feasible.

It is important for project managers to be aware of the availability and due dates for all tasks within a project. They should also carefully read through all directions for the project's activities to effectively plan their time and ensure they are working progressively on the project throughout the week.

No related questions found