Which of the following is NOT something that must be done in order for MS Project to calculate earned value amounts for a project schedule?

a) Setting baseline
b) Entering actual work
c) Assigning resources
d) Defining constraints

User Letoncse
by
7.9k points

1 Answer

7 votes

Final answer:

Defining constraints is not required for calculating earned value in MS Project; whereas setting a baseline, entering actual work, and assigning resources are essential.

Step-by-step explanation:

The question deals with the process of calculating earned value in MS Project, a project management software. Defining constraints is NOT a requirement for MS Project to calculate earned value amounts for a project schedule; however, setting a baseline, entering actual work, and assigning resources are necessary steps in this process. Earned value management (EVM) is a project management technique that combines measurements of project performance related to scope, schedule, and cost.

User Abdul Raziq
by
8.6k points