Which of the following is NOT something that must be done in order for MS Project to calculate earned value amounts for a project schedule?

a) Setting baseline
b) Entering actual work
c) Assigning resources
d) Defining constraints

User Letoncse
by
7.7k points

1 Answer

7 votes

Final answer:

Defining constraints is not required for calculating earned value in MS Project; whereas setting a baseline, entering actual work, and assigning resources are essential.

Step-by-step explanation:

The question deals with the process of calculating earned value in MS Project, a project management software. Defining constraints is NOT a requirement for MS Project to calculate earned value amounts for a project schedule; however, setting a baseline, entering actual work, and assigning resources are necessary steps in this process. Earned value management (EVM) is a project management technique that combines measurements of project performance related to scope, schedule, and cost.

User Abdul Raziq
by
8.4k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.