The Critical Path Method (CPM) of scheduling is

A. A mathematical analysis technique for schedule development.
B. A technique that uses weighted averages to calculate project duration.
C. A technique that uses sequential network logic for schedule development.
D. A technique that allows for probabilistic treatment of both network logic and activity duration estimates.

1 Answer

5 votes

Final answer:

The Critical Path Method (CPM) is a technique that uses sequential network logic for schedule development. It helps project managers determine the minimum amount of time required to complete a project.

Step-by-step explanation:

The Critical Path Method (CPM) of scheduling is a technique that uses sequential network logic for schedule development. It is commonly used in project management to determine the minimum amount of time required to complete a project. The CPM identifies the critical path, which is the sequence of activities that must be completed on time in order to meet the project deadline. This helps project managers allocate resources and prioritize tasks.