Answer:
Predetermined manufacturing overhead rate= $29 per machine hour
Step-by-step explanation:
Giving the following information:
Estimated machine-hours 33,100
Estimated variable manufacturing overhead $5.72 per machine-hour
Estimated total fixed manufacturing overhead $770,568
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (770,568/33,100) + 5.72
Predetermined manufacturing overhead rate= $29 per machine hour