The schedule forecasts will be an output of what process?

1) Control schedule
2) Forecast schedule
3) Develop schedule
4) Develop project management plan

User Anki
by
8.7k points

1 Answer

3 votes

Final answer:

The schedule forecasts are an output of the Develop schedule process.

Step-by-step explanation:

The schedule forecasts are an output of the Develop schedule process. This process is part of the project management discipline and involves analyzing various factors to create an accurate project schedule.