Final answer:
The NPV for the project at a required return of 15 percent is $6,499.65, while at a required return of 38 percent it is -$3,909.82.
Step-by-step explanation:
To calculate the NPV (Net Present Value) for the project, we need to discount each cash flow at the required return rate and sum them up. Using the formula NPV = CF₀/(1+r)⁰ + CF₁/(1+r)¹ + CF₂/(1+r)² + CF₃/(1+r)³, where CF represents the cash flow and r is the required return rate, we can calculate the NPV.
At a required return of 15 percent, the NPV for this project is:
NPV = -26,000/(1+0.15)⁰ + 19,000/(1+0.15)¹ + 14,000/(1+0.15)² + 8,000/(1+0.15)³ = $6,499.65
At a required return of 38 percent, the NPV for this project is:
NPV = -26,000/(1+0.38)⁰ + 19,000/(1+0.38)¹ + 14,000/(1+0.38)² + 8,000/(1+0.38)³ = -$3,909.82