147k views
2 votes
Another project manager who has been assisting you has created an optimistic estimate of RM 10,450, a most likely estimate of RM 22,300, and a pessimistic estimate of RM 36,650 for a portion of this project. What is the three-point estimate in this scenario?

User Poliquin
by
8.0k points

1 Answer

3 votes

Final answer:

The three-point estimate for the project, based on the given optimistic, most likely, and pessimistic estimates, is RM 22,716.67.

Step-by-step explanation:

The three-point estimate is a technique used in project management to estimate the potential costs of a project based on three scenarios: optimistic, most likely, and pessimistic. To calculate the three-point estimate, you typically use the formula (Optimistic Estimate + 4 × Most Likely Estimate + Pessimistic Estimate) / 6. In the scenario you've provided, the three-point estimate would be calculated as follows:

(RM 10,450 + 4 × RM 22,300 + RM 36,650) / 6 = (RM 10,450 + RM 89,200 + RM 36,650) / 6 = RM 136,300 / 6 = RM 22,716.67.

Therefore, the three-point estimate for the project is RM 22,716.67.

User Andrei Fedorov
by
7.3k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.