96.3k views
16 votes
Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $6,000 for direct materials, $9,900 for direct labor, and $7,128 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $3,000 for direct materials and $4,900 for direct labor.

Required:
Calculate the overhead cost be added to Job W at year-end

User AdamV
by
4.9k points

1 Answer

6 votes

Answer:

$6,811

Step-by-step explanation:

Job V had $9,900 of direct labor and $7,128 of overhead was applied to the job

= $9,900 ÷ $7,128

= $1.39 overhead rate.

This means that the application was based on taking $9,900 of Direct labor × $1.39 rate = $7,128 overhead

For Job W, take $4,900 DL × same $1.39 rate = $6,811

Therefore, the overhead cost to be applied to job w at year end is $6,811

User Jose Sosa
by
5.1k points