Clean out 2 inches in size or less are required to have a clearance ___________" in front of the clean out.

a: 6
b: 12
c: 18
d: 24

User Sanchay
by
8.6k points

1 Answer

3 votes

Final answer:

Clean outs of 2 inches or smaller require an 18" clearance in front of them to allow for proper maintenance and emergency access by plumbing professionals.

Step-by-step explanation:

The question pertains to plumbing standards regarding the installation of clean outs. These are access points in a plumbing system that allow for blockages to be removed and for the system to be cleaned. According to plumbing codes and standards, clean outs that are 2 inches or smaller in size are required to have a clearance of 18" in front of the clean out. This clearance is crucial to allow enough space for a plumber or technician to access the clean out for maintenance or during an emergency.

User AndrewF
by
7.2k points