Final answer:
The total lead time for order fulfillment at Mittel Rhein AG is the sum of inspection, wait, process, move, and queue times, which amounts to 23.0 days.
Step-by-step explanation:
The total lead time for order fulfillment is calculated by adding each of the reported times involved in the process. According to the data provided by Mittel Rhein AG, the following times are added:
- Inspection time: 0.3 days
- Wait time: 14.0 days
- Process time: 2.7 days
- Move time: 1.0 day
- Queue time: 5.0 days
By summing these values, we get:
0.3 + 14.0 + 2.7 + 1.0 + 5.0 = 23.0 days
Therefore, the total lead time for order fulfillment at Mittel Rhein AG is 23.0 days.