Final answer:
A Change Order must be issued to address changes to contract drawings after an RFI during bidding.
Step-by-step explanation:
When the contractor submits a request for information (RFI) during bidding and there is a need to address a change in the contract drawings as a response from the architect, a Change Order must be issued. A Change Order is a formal direction for any change to the scope of work, which can include additions, deletions, or other modifications that impact the original contract. It's essential to note that a Change Order can only be implemented after both parties agree to the new terms and it is formally documented.
When the architect's response to the contractor's request for information (RFI) entails a change to the contract drawings during bidding, a Change Order must be issued to address this change. A Change Order is a formal written document that modifies the original contract between the contracting parties, in this case, the contractor and the architect. It outlines the specific changes to the contract drawings, along with any corresponding adjustments to the scope of work, schedule, and cost.