Answer:
a. Assuming that the investors are concerned only about expected returns, stockholders would prefer Project 2. It yields more returns with the high risk variability attached to the better yield of $20,000.
b. Bondholders would prefer Project 1. It yields good returns with moderate risk variability. Bondholders are generally risk-averse. They avoid risk wherever possible.
Step-by-step explanation:
a) Data and Calculations:
Project 1 Project 2
Investment $11,000 $11,000
Expected Returns $12,000 $12,500
Bond issue = $10,000 with interest rate of 10%
Expected Returns for Project 1:
Yield Probability Expected Value
$11,000 0.5 $5,500
$13,000 0.5 $6,500
Total expected returns = $12,000
Expected Returns for Project 2:
Yield Probability Expected Value
$5,000 0.5 $2,500
$20,000 0.5 $10,000
Total expected returns $12,500