When coring between floors, a watchman should be placed

Select one:
O a. above the hole being cored
O b.
behind the coring drill
Oc below the hole being cored
O d. on the roof
to warn workers, catch water flow, and control the waste core

1 Answer

3 votes

Final answer:

When coring between floors, the watchman should be placed below the hole being cored to ensure worker safety and prevent damage to lower floors.


Step-by-step explanation:

When coring between floors, a watchman should be placed below the hole being cored. This is because the watchman's position allows them to warn workers and catch any water flow or waste core debris that may fall from the drilling process, protecting the workers and preventing any potential damage to the lower floors. Placing the watchman above the hole or on the roof wouldn't be effective in achieving these safety objectives.