124k views
4 votes
20 men working 6 hours a day can finish a work during 10 days. 4 men got seek and didn't work How many hours a day should work other 16 men to finish the work during (a) 10 days? (b) during 15 days?​

2 Answers

5 votes

Explanation:

subs8biiisowm9bbbs9 to

User Klor
by
8.0k points
4 votes

Answer:

B) 15 days

Explanation:

Total Work = (Number of men) x (Hours worked per day) x (Number of days)

Using this formula, we can find the total amount of work to be done in the scenario given in the question:

Total Work = (20 men) x (6 hours per day) x (10 days) = 1200 hours

(a) To find out how many hours a day the remaining 16 men should work to finish the work in 10 days, we need to subtract the work that was not done due to the absence of the 4 men:

Remaining Work = Total Work - Work not done by 4 men

Remaining Work = 1200 - (4 men) x (6 hours per day) x (10 days)

Remaining Work = 840 hours

To finish the remaining work in 10 days, the 16 men would need to work:

Hours per day = Remaining Work / (Number of men) x (Number of days)

Hours per day = 840 / (16 men) x (10 days)

Hours per day = 5.25 hours

Therefore, the 16 men would need to work 5.25 hours per day to finish the work in 10 days.

(b) To find out how many hours a day the remaining 16 men should work to finish the work in 15 days, we need to calculate the total amount of work that needs to be done each day:

Daily Work = Total Work / Number of days

Daily Work = 1200 / 15

Daily Work = 80 hours

To finish the daily work of 80 hours, the 16 men would need to work:

Hours per day = Daily Work / Number of men

Hours per day = 80 / 16

Hours per day = 5 hours

Therefore, the 16 men would need to work 5 hours per day to finish the work in 15 days.

User Evan Frisch
by
7.9k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.